SERVICES

Commissioning & Integration Services

Complete Solutions for Substations and Power Systems

 

Engetecnica manages and integrates highly complex electrical infrastructure projects, including the complete construction of power substations, new electrical power systems, and expansions or upgrades to existing systems.

By outsourcing your commissioning and integration activities to our expert team, your organization can stay focused on its core operations while we ensure a smooth, safe, and efficient start-up process for your power systems.

Thanks to our structured organization and multidisciplinary professionals, we deliver seamless execution — from planning through energization.

Our Work Process

Equipment Testing

Using state-of-the-art instruments, we test all equipment in accordance with national and international standards to ensure performance, integrity, and long-term reliability.

Functional Tests

We verify electrical control, signaling, interlocks, and activation circuits to ensure accurate logic and reliable operation.

Protection Curve Validation

We confirm relay settings and selectivity studies, ensuring optimal coordination between protection elements.

Integrated System Tests

We perform end-to-end validation of electrical systems, including interlocks, automation, local and remote controls, voltage and current circuits, and logic diagrams.

Energization Monitoring

After final commissioning, we supervise the energization process to ensure proper functioning and safety of the installation.

Field Services Portfolio

Power Transformers & Reactors

  • Hydraulic and gas circuit pressurization checks
  • TLI (Tank Loss Index) calculations for GVO breakers
  • Bushing hot gluing and CT testing
  • Oil sampling and analysis
  • Contact and insulation resistance tests
  • Pressurization and spring timing
  • SF6 moisture content measurement

Disconnectors

  • Grounding and structure testing
  • Contact resistance and insulation measurements
  • Motor insulation and timing tests

Inductive Voltage Transformers (PTs)

  • Winding insulation power factor
  • Polarity and ratio testing
  • Electrical resistance measurements

Current Transformers (CTs)

  • Saturation curve analysis
  • Polarity and ratio validation
  • Insulation and resistance testing

Lightning Arresters

  • Grounding resistance measurements
  • Discharge counter operation
  • Insulation resistance and power loss factor

Capacitor Banks

  • Unit and phase capacitance
  • Shelf and capacitor insulation testing
  • Resistor electrical resistance

Blocking Coils

  • Inductance, resistance, and insulation validation

Medium Voltage Cables (15–23 kV)

  • Visual and insulation testing
  • DC voltage withstand tests

Auxiliary Services Commissioning

Stationary Batteries

  • Equalization charging
  • Capacity discharge/recharge cycle
  • Density and voltage tests
  • Internal resistance measurement
  • Connection integrity and torque checks

Battery Chargers

  • Functional simulations and instrument calibration
  • Ripple and voltage regulation tests
  • Alarm, polarity, fuse, and safety device checks

Auxiliary Service Transformers

    • Oil testing and analysis
    • Electrical and insulation resistance
    • Ratio and stress tests

Protection & Control Panel Commissioning

Panels

  • Protection philosophy verification
  • Heating and measurement systems analysis
  • Voltage and current injection
  • Wiring continuity and insulation
  • Status indicator and fuse verification

Lockout Relays (86 Relay)

  • Trip logic testing
  • Interlock and trip transfer checks
  • Full relay-circuit breaker signaling validation